Installation & commissioning

From the crate into production, with a signature

Goods receipt, assembly, calibration, risk assessment, trial operation and formal handover. With a protocol that gets signed.

What handover means

Handover means it produces, not that it stands upright

We consider a project deliverable when the robot performs the intended task at your pace, with your operators and without us standing next to it.

Until that point we run acceptance tests against criteria agreed in writing before installation: cycle time, success rate, recovery time after an error.

The package

What we do on site

01

Goods receipt and check

We inspect the equipment with the manufacturer before it goes onto the line.

02

Mechanical installation

Bases, charging points, guarding, floor marking.

03

Electrical and network

Power, Wi-Fi or 5G, an isolated VLAN for the robots.

04

Calibration and programming

We set up the tasks and store them as reusable programmes.

05

Risk assessment

To ISO 12100 and ISO 10218, documented for your file.

06

Acceptance tests

We run the agreed protocol and sign it together.

Timeline

A typical project in four weeks

Week 1: site preparation

Electrical work, network, charging points and marking before the equipment arrives.

Week 2: installation

Assembly, calibration, first tests without production.

Week 3: trial operation

Parallel operation with the existing setup, measurement and correction.

Week 4: handover

Acceptance tests, operator training, signed protocol.

Frequently asked questions

Frequently asked questions

In most cases no. We work in parallel and switch during a planned stop or a low-load shift.
The individual robot carries its own marking. For the overall assembly created at your site we prepare the risk assessment and the technical file.
Tasks are stored as programmes. A product change means a new setup, not a new installation.

Want a timeline for your site?

Send us a floor plan or photos and you get a realistic schedule.